Progress of Housing for All Scheme : Loksabha Q&A
लोकसभा में आवासन और शहरी कार्य मंत्री से "सभी के लिए आवास योजना" से सम्बंधित सवालों का सरकार की तरफ से जवाब देते हुए कहा कि पिछले 12 महीनों में लोगों को आवास मुहैया कराने के लिए प्रधानमंत्री आवास योजना (शहरी) इस कार्य में अग्रसर है। पिछले 12 महीने में कुल संस्वीकृत 1,07,50,082 आवासों में से 21,73,749 आवास ही संस्वीकृत हुए हैं।
कोविड-19 महामारी के चलते हुए लॉकडाउन के कारण सामानों की आपूर्ति में बाधा, निर्माण श्रमिकों की अनुपलब्धता के कारण काम पर बहुत प्रभाव पड़ा है, काम धीमा हो गया है।
GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO: 876
ANSWERED ON: 17.09.2020
Housing for All
Sunil Kumar Singh
Kaushal Kishore
Arjunlal Meena
P.P. Chaudhary
Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to state:-
(a) the number of people who have been benefitted under “PM Housing For All” scheme in past 12 months;
(b) whether the Government has considered increase in allotment of funds under PM-HFA scheme to complete its target of Housing For All by 2022 and if so, the details thereof; and
(c) whether COVID-19 has impacted the construction and allotment of houses under the scheme and if so, the details thereof?
ANSWER
(a): In pursuance of the Government’s vision of “Housing for All” by 2022, Ministry of Housing and Urban Affairs (MoHUA) is implementing Pradhan Mantri Awas Yojana (Urban) PMAY(U)] for providing assistance to States/ Union Territories (UTs) for addressing the housing requirement in urban areas.
Out of total 1,07,50,082 houses sanctioned so far under the scheme, 21,73,749 houses have been sanctioned in the past 12 months.
(b): Yes, Sir. The Ministry has evolved a strategy to meet the funding requirement for PMAY(U) through budgetary resources as well as Extra Budgetary Resources(EBR). Apart from year-on-year budgetary allocation, the Union Cabinet has approved ?60,000 crore of EBR of which ?48,000 crore have already been raised.
(c): On account of lockdown due to ongoing COVID-19 pandemic, construction activities under the scheme were affected for a short period due to disruption in supply chain of construction materials and non-availability of construction labour. However, construction work has since resumed after the lockdowns were lifted in phases as per advisories issued by Central/State/UT Governments. All efforts are being made to accelerate the pace of construction and complete the projects within the given timelines.
*****
Source: [English Version] [Hindi Version]
Post a Comment